Week One Completed of New Pass Dredging Project
Posted Date:
8/25/2016
The first week of the New Pass Dredging Project resulted in the dredging of approximately 12,226 cubic yards of sand.

August 25, 2016 | The first week of the New Pass dredging project resulted in the dredging of approximately 12,226 cubic yards of sand. Norfolk Dredging Company is starting at the southern end of L’Ambiance and working north. Work is progressing and additional shore pipe pieces have been delivered to the beach to progress northward to Regent Place.  Dredging operations will be occurring 24/7 to complete this work as quickly as possible.  The South End/New Pass beachfill operation is expected to last roughly 4 weeks.

The Town and Norfolk Dredging Company are currently watching the developing tropical weather situation and making a plan for severe weather should it arise.

New Pass Dredging Project South End at L'Ambiance  

 

 
 
Town of Longboat Key    -    501 Bay Isles Road Longboat Key, FL 34228    -    Phone: (941) 316-1999 Fax: (941) 316-1656
Site Map   |   Contact Us    |   Powered by MunicipalCMS
Find us on Facebook Follow us on Twitter Get our RSS Feeds Sign up for E-News  
Under Florida law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public-records request, do not send electronic mail to this entity. Instead, contact this office by phone or in writing.